Brookhaven National Laboratory Data Center Mechanical Systems (Mission Critical)
A 12.5 million dollar, 2-year project consisted of performing all mechanical work necessary for the construction of a new Data Center at the Brookhaven National Laboratory. The main features of the work included but were not limited to the following:
· Water cooled electrical centrifugal chillers
· Cooling towers and associate structural support
· Chilled water and condenser water piping system
· Computer room air conditioners (CRAC) units, AHUs and heat exchangers
· High-flow service pumps, surge tank and associated process piping, fittings and valves
· Instrumentation and controls necessary to communicate with the BMS system.
Click thumbnails to view larger images.
Eisenhower Barracks Mechanical Renovations
Click thumbnails to view larger images.
HELEN HAYES HOSPITAL MECHANICAL UPGRADES & ASBESTOS ABATEMENT
Abatement of Asbestos of existing mechanical systems. All State Construction worked within affected buildings including removal of existing mechanical plumbing and electrical systems in each room and the replacement of new mechanical and plumbing, piping, equipment and electrical to provide a complete active system. All State also provided an energy supply, including oil, gas and steam supply systems.
Click thumbnails to view larger images.
UCONN KELLOGG DAIRY ROBOTICS BUILDING
All State Construction Renovated the Kellogg Dairy Center to allow for the installation of two (2) robotic milkers which feed/milk the cows automating the milking process. The addition created a contiguous space adjoined to the present end wall at the west end of the existing open stall cow barn of approximately 2,767 GSF as well as updating the mechanical system of the building. Site development included a new circulation driveway connecting to the existing parking lot to the northwest with gravity retaining walls. Storm water basins, erosion and sedimentation control were utilized to support the existing natural ecosystem
Click thumbnails to view larger images.
Sacred Heart University
Mechanical Contractor for the new Residence Hall.
All State Construction provided all of the mechanical work for Bergoglio Hall, the new three-story 80,000-square-foot Residence Hall at Sacred Heart University, new home to over 200 sophomore students.
Click thumbnails to view larger images.
Westfiled Trumbull Mall
Emergency Smoke Evacuation System
Click thumbnails to view larger images.
MacArthur Long Barracks, Westpoint Academy, NY
Mechanical Contractor for the renovations of MacArthur Long Barracks
MACARTHUR LONG BARRACKS RENOVATION VIDEO
Click thumbnails to view larger images.
University of Connecticut
Main Campus Data Center Upgrade
The mission critical project consisted of complete renovations and upgrades to the main campus Data Center while maintaining service with no interruptions.