Brookhaven National Laboratory Data Center Mechanical Systems (Mission Critical)

Project Description

A 12.5 million dollar, 2-year project consisted of performing all mechanical work necessary for the construction of a new Data Center at the Brookhaven National Laboratory. The main features of the work included but were not limited to the following:

·         Water cooled electrical centrifugal chillers

·         Cooling towers and associate structural support

·         Chilled water and condenser water piping system

·         Computer room air conditioners (CRAC) units, AHUs and heat exchangers

·         High-flow service pumps, surge tank and associated process piping, fittings and valves

·         Instrumentation and controls necessary to communicate with the BMS system.

Gallery

Click thumbnails to view larger images.